The three statements, working capital, ratios, forecasting, variance analysis, costing, capital budgeting, valuation and the modelling and Excel work that fills the day, plus the fit questions about why this seat. Every question is either traced to a named firm from a public candidate report, or tagged at desk level when we could not trace it — we do not invent attributions.
100 questions, mapped to the firms that asked them
- Questions
- 100
- Traced to a firm
- 42
- Firms
- 28
- Updated
- September 2026
041A cost centre came in under budget. Why might that be bad news?Corporate FP&ABusiness finance
Say this
Because a favourable variance against a fixed budget can just mean the activity did not happen. Before I call it a saving I flex the budget for actual volume and check whether the underspend is a deferral, a phasing difference or a capability we have quietly stopped funding.
Then walk it
- First, flex it. If the budget assumed 100 units of activity and you did 80, a variable cost line should be 20 percent lower. Reporting that as a saving against the original budget is simply wrong, and flexed budgeting exists to stop it.
- Second, test whether it is timing. Maintenance deferred, recruitment delayed, a marketing campaign slipped to next quarter. That is not a saving, it is a liability with a later date, and it will make next quarter look terrible.
- Third, ask what did not get done. Underspent training, safety maintenance, IT security or R&D produces a favourable variance this year and a problem in two. This is the version that damages the business while flattering the pack.
- Fourth, check for an accrual error. Missing invoices and under-accrued costs look identical to an underspend until the true-up lands.
- So on the monthly pack I would label variances as volume-driven, timing or genuine run-rate, and only the third counts as a saving. Without that split, cost variance reporting is close to meaningless.
- This is also where standard costing earns its keep. Splitting a materials variance into price and usage tells you whether procurement bought cheaper or the plant wasted less, and those are different wins with different owners.
Where candidates lose it
Accepting a favourable variance at face value. The interviewer wants to hear 'flex the budget for volume' and 'separate timing from run-rate'. Naming deferred maintenance as the dangerous case is what makes it sound like experience.
Expect next
- How would you present timing variances so nobody claims them as savings?
- What is the difference between a materials price and usage variance?
- How do you stop under-accrual creating false savings?