Fin Maverick
Foundations VocabularyAccounting & ReportingEconomics & MacroQuant Methods & ProgrammingBusiness & Company AnalysisCorporate Finance & ValuationBehavioural Finance
Banking & Market InfrastructureFixed Income & RatesDerivatives & Structured ProductsPublic EquitiesTransactions & DealsPortfolio ConstructionFunds & AMCs
Private Markets & AlternativesRisk, Treasury & ControlAI & Digital FinanceStochastic Calculus & PricingWealth & Personal FinanceIndian Markets & RegulationProfessional Practice
CalculatorComparison
Frameworks
Explore Bootcamps
Equity ResearchPortfolio ManagementMutual Fund MasteryFinancial LiteracyInvestment Banking Analyst
Private Equity AnalystHedge Funds AnalystBreaking Into VCBreaking Into QuantsAI For Finance
Financial Analyst ProgramRisk Management ProgramPrivate Wealth ManagementDebt Capital MarketsDerivatives Foundation
Explore Internships
Equity Research InternMutual Fund Intern
Portfolio Management InternFinancial Literacy Intern
Explore Micro Courses

Equity Research6

Writing an Investment ThesisBuilding a Discounted Cash FlowReading an Annual Report FastReading a Sector Before a CompanySpotting Quality of Earnings Red FlagsBuilding a Revenue Forecast From Drivers

Portfolio Management3

Rebalancing: When, Why and What It CostsStrategic and Tactical Asset AllocationMeasuring Risk in a Portfolio

Mutual Fund Mastery3

Comparing Funds Without Being FooledHow a NAV Is Struck and Which Day You GetReading a Fund Factsheet Properly

Derivatives Unlocked4

Hedging a Real ExposureThe Greeks, PracticallyFutures, the Basis and What Moves ItReading an Option Payoff

AI For Finance2

Retrieval and Grounding for FinanceDocument Extraction in Finance

Breaking Into Quants4

Backtesting a StrategyHypothesis TestingCleaning Financial DataRegression for Finance

Breaking Into VC3

Sizing a MarketReading a Term Sheet as a FounderHow a Venture Round Actually Works

Financial Analyst Program4

Common Size and Trend AnalysisReading a Cash Flow StatementRatio Analysis That Says SomethingBuilding a Working Capital Schedule

Risk Management Program2

Credit Exposure and How It Is ReducedValue at Risk and What It Hides

Investment Banking Analyst3

Precedent Transactions and Why They DifferReading a Term Sheet StructurallyBuilding a Comparable Companies Table

Private Wealth Management3

Tax Aware Portfolio DecisionsBuilding a Client Risk ProfileGoal Based Planning Arithmetic

Debt Capital Markets3

Analysing an Issuer's CreditDuration and What It Does Not Tell YouBond Pricing and Yield Mechanics

Private Equity Analyst2

Fund Waterfalls and CarryThe LBO in Structure

Hedge Funds Analyst2

Short Selling MechanicsLong Short Mechanics
Courses
Explore Career Roadmaps
Investment Banking AnalystEquity Research AnalystVC AnalystPrivate Equity AnalystHedge Funds Analyst
Quant AnalystAI For FinanceFinancial Analyst ProgramPrivate Wealth ManagementDebt Capital Markets
Risk Management ProgramDerivatives FoundationPortfolio ManagementMutual Fund Mastery
PartnershipsShowdown
Log inSign up
Investment Banking Analyst · CoreTrack
1Financial Accounting, Reporting & Analysis
iAccounting System and Standards
Financial AccountingDebits and CreditsAccrual and Cash AccountingAccounting Policies, Estimates and…The Matching PrincipleDouble-Entry AccountingGoing ConcernInd AS and IFRSWhy Two Honest Companies…
iiFinancial Statement Architecture
The Three Financial StatementsConsolidated Financial StatementsStandalone and Consolidated Statements…How to Read a…How to Perform Trend…Which Accounting Rules Apply…
iiiIncome Statement, Profitability and Tax
The Income StatementRevenue vs Income vs ProfitHow to Read an Income StatementThe Profit LadderEBITDA and EBIT Compared,…EBIT vs EBT vs PATOperating ExpenditureTax-Loss CarryforwardWhy a Company's Effective…Deferred TaxDiluted EPSEffective Tax Rate
ivBalance Sheet and Capital Employed
The Balance SheetAsset TypesCapital EmployedReturn on Capital EmployedLiabilitiesBook ValueRetained EarningsOff-Balance-Sheet FinancingHow to Read a Balance SheetTangible Net Worth
vCash Flow and Liquidity
The Cash Flow StatementOperating, Investing and Financing…Operating Cash FlowProfit vs Cash FlowCash Flow From Operations vs EBITDARevenue Growth vs Operating Cash FlowHow to Read a Cash Flow StatementHow to Reconcile Cash…
viRevenue, Receivables and Working Capital
The Working Capital CycleThe Working Capital CycleReturn on Invested CapitalHow Working Capital Affects Cash FlowAccrued and Deferred RevenueRevenueHow to Analyse Revenue QualityAccounts PayableAccounts ReceivableExpected Credit Loss
viiInventory, Cost Accounting and Margins
Cost AbsorptionInventoryCost of Goods SoldFIFO vs Weighted Average CostAmortised Cost vs Fair ValueInventory Write-DownsMargin AnalysisContribution MarginOperating LeverageGross Profit vs Gross MarginHow to Analyse Profit MarginsHow to Interpret Operating…
viiiFixed Assets, Leases and Intangibles
DepreciationDepreciation MethodsAmortisation vs DepreciationAsset ImpairmentCapital ExpenditureAsset Efficiency and Capital IntensityProperty, Plant and EquipmentIntangible AssetsOperating Lease vs Finance…How to Analyse Capex…Why Capitalising Costs Increases…
ixDebt, Equity and Financial Instruments
Equity on the Balance SheetDebt TypesNet Debt and LeverageDebt vs Equity Accounting ClassificationHow to Analyse Debt…Convertible BondsInterest in the AccountsShare CapitalShare DilutionHybrid Instruments
xConsolidation and Business Combinations
ControlSubsidiaryGoodwillAssociate CompanyJoint Venture vs Associate…Intercompany EliminationsThe Equity MethodHow to Analyse Group…
xiCash, Investments and Financial Assets
Cash and Cash EquivalentsHow to Analyse Cash…The Fair Value HierarchyHow to Interpret a…Financial Asset ClassificationMarketable Securities and Short-Term Investments
xiiFinancial Ratios and Performance Diagnostics
Return on CapitalDuPont AnalysisHow to Perform Common-Size AnalysisDebt to EquityLiquidity RatiosLeverage and Coverage RatiosReturn on Equity and the DuPont DecompositionWhich Financial Ratios Matter…
xiiiEarnings Quality, Red Flags and Forensics
Earnings QualityHow to Prepare for…Channel StuffingEarnings ManagementHow to Analyse Related-Party…How to Spot Accounting…Why Frequent Exceptional Items…What an Auditor Change…
xivAnnual Reports, Notes and Disclosure Reading
Notes to the AccountsManagement Discussion and AnalysisSegment ReportingShareholding PatternPro Forma FinancialsAnnual Report vs Investor…How to Read an Annual Report
xvAudit, Assurance and Reporting Reliability
The Statutory Audit and the AuditorAudit MaterialityEmphasis of MatterFinancial RestatementInternal AuditLimited ReviewKey Audit MattersInternal Controls Over Financial ReportingThe Audit OpinionAuditor Independence
2Corporate Finance & Valuation
iCorporate Finance Fundamentals
Corporate FinanceCorporate Finance vs AccountingAgency CostsThe Financial ObjectiveThe Financing DecisionThe Investment DecisionProfit Maximisation vs Value…How Capital Allocation Affects…
iiTime Value of Money
Time Value of MoneyTime Value of MoneyCompoundingNominal and Effective Annual RatesThe Discount RateNominal vs Real Discount RateAnnuity vs Perpetuity
iiiCash Flow and Value Drivers
ReinvestmentReinvestment RateRevenue GrowthRevenue Growth vs ReinvestmentReturns in Corporate FinanceValue DriversOperating MarginEconomic ProfitFCFF vs FCFEHow to Normalise Earnings…
ivCost of Capital
The Cost of CapitalCost of CapitalSunk Cost vs Opportunity CostHow to Estimate a…Levered and Unlevered BetaCountry Risk PremiumEquity Risk PremiumThe Risk-Free Rate
vCapital Structure
Capital StructureHow to Analyse a…Financial LeverageOperating Leverage vs Financial…RecapitalisationDebt FinancingDebt CapacityGross Debt vs Net DebtEquity FinancingHow Leverage Can Increase…Refinancing RiskFinancial Distress
viCapital Budgeting
Capital BudgetingSunk CostsDiscounted PaybackPayback vs Discounted PaybackNet Present ValueInternal Rate of ReturnProject AppraisalIndependent vs Mutually Exclusive…How to Resolve NPV and IRR Conflicts
viiWorking Capital Finance
Capital RationingWorking Capital FinancingExcess CashCash ManagementShort-Term Financing
viiiPayout Policy
Payout PolicyPayout and Return of CapitalDividendsDividend Yield vs Payout RatioSignallingShare BuybacksDividend vs Buyback
ixValuation Fundamentals
ValuationValuation RangeFCFF vs FCFE ValuationSOTP vs Consolidated ValuationHow to Build a DCF ValuationHow to Build a…How to Build a…Firm Value and Equity ValueReplacement CostShareholder ValueEnterprise-to-Equity Value BridgeSum-of-the-PartsEnterprise Value vs Equity ValueValue vs PriceAsset Value vs Earnings ValueBook Value vs Adjusted Book ValueLiquidation Value vs Going-Concern…
xDiscounted Cash Flow
Discounted Cash FlowTerminal ValueNormalisationThe Forecast HorizonIncremental Cash FlowFree Cash Flow to FirmDiscounted Cash FlowBase Case vs Bull Case vs Bear CaseTwo-Stage vs Three-Stage DCFForward vs Historical FinancialsOperating vs Non-Operating AssetHow to Forecast Free Cash FlowHow to Audit a DCF Model
xiRelative Valuation
Relative ValuationDCF vs Relative ValuationConglomerate DiscountComparable Company AnalysisHow to Select Comparable CompaniesTrading MultiplesTrading Multiples
xiiTransaction Valuation
Transaction ValueDeal Value vs Enterprise ValueSources and UsesAccretion and DilutionHow to Analyse Accretion…Leveraged BuyoutManagement RolloverMinority Interest in ValuationControl Premium vs Minority DiscountPrecedent TransactionsLBO ReturnsTrading Comps vs Precedent TransactionsStrategic Buyer vs Financial BuyerHow to Build an…
xiiiValuation Discipline
Decision Rules in ValuationHow Valuation Ranges Improve…Implied AssumptionsImplied GrowthBase, Bull and BearScenario vs Sensitivity AnalysisMargin of SafetyHow to Check Discount…
3Transactions & Corporate Finance
iCapital Raising
Private PlacementRights Issue or Private PlacementSecondary SalePrimary Issue or Secondary SaleRefinancingConvertible Securities in a RaiseNet DebtUse of ProceedsAccretion Or DilutionHow To Analyse Financing…How To Map The…
iiMergers and Acquisitions
SynergyAsset Purchase or Share PurchaseExchange Ratio or Purchase PriceThe Deal RationaleDeal TermsIntegrationThe Integration PlanThe Value Creation PlanThe Synergy RegisterSynergy or Cost SavingThe Post-Merger ReviewMerger or AcquisitionReinvestment or Acquisition Spend
iiiThe Transaction Process, Governance and Communications
What a Transaction Is,…Signing and ClosingThe Term SheetTerm Sheet or Definitive AgreementThe MandateThe Data RoomThe Letter of IntentMaterial Information in a DealMaterial or Confidential InformationThe Deal Communication PlanInvestor or Employee MessageThe LeakThe Deal TeamThe Independent CommitteeHow an Information Barrier…Market SoundingThe Deal Stakeholder MapThe Deal TimelineDeal Outcome or Process QualityHow to Map a…The Long-Stop DateDeal RumoursDue Diligence or AuditConstruction Risk or Operating RiskRegulatory Approval or Third-Party ConsentExclusivity or ConfidentialityConditions Precedent or Subsequent
ivTransaction Documentation
Representations and WarrantiesThe Definitive AgreementThe Disclosure ScheduleThe Non-CompeteBreak Fee, Reverse Break…Termination RightsIndemnity, Covenant and UndertakingLimitation of LiabilityCompletion Accounts vs Locked BoxIndemnity vs EscrowHoldback vs EscrowHow to Build a…
vTransaction Valuation
ConsiderationBuilding a Consideration AnalysisComparable Companies in a DealEnterprise Value in a DealEquity ValuePurchase Price MechanicsThe Reservation PriceThe Fairness OpinionTransaction Risk and Integration RiskConflict of Interest and…Transaction Announcement and Market RumourBuilding a Diligence Workplan…Framing a Valuation Inside a TransactionKeeping a Transaction Decision…Writing a Transaction Case Study
viDeal Execution
Deal CertaintyConditions Precedent, Regulatory and…Deal Narrative vs Investment CaseThe Closing ChecklistMaterial Adverse ChangeClosing Deliverables
viiRestructuring
RestructuringHow to Map a…Demerger, Spin-Off and Carve-OutInsolvencyThe Distressed SaleThe Asset SaleThe Scheme of ArrangementThe TurnaroundDemerger vs Spin-OffTurnaround vs Debt Restructuring
viiiProject Finance
Project FinanceProject Finance vs Corporate FinanceHow to Map a…How to Review Project-Finance…The Project LenderSponsor vs LenderThe ConcessionDebt Service, the Cover…Debt Capacity and Debt OutstandingThe Offtake AgreementPolitical RiskHow to Build a…The Special Purpose VehicleCoverage RatiosDSCR and Interest Coverage
ixCapital Allocation
Capital AllocationHow to Build a…Growth Capex and Maintenance CapexThe Capital BudgetReturn of CapitalDebt Repayment or Share Repurchase

The Capital Budget: Dividing One Period of Capital

A capital budget is one period's capital stated as a single total and then divided: what the business generates, what cash it starts with, and what it can borrow inside a stated ceiling, set against every claim on that total. Claims that are not optional come out first. The remainder is the only money any competing use is actually arguing over.

The comparison sheet is already built. How a period's capital is counted, how each claim is sized in rupees and in periods, and how a return gets a stated basis are settled elsewhere. Turning that sheet into a budget is the narrower and more useful job. A budget is a document with one total at the top and a division underneath it. The sheet compares. The budget divides. Comparing and dividing are not the same job, and confusing them is how a company ends up with an excellent analysis and no decision.

A budget is three things. One period. One total. One division. ONE PERIOD, STATED: the twelve months being budgeted ONE TOTAL, BUILT NOT ASSERTED generated + already held + borrowable inside a ceiling, less what is committed ONE DIVISION, ACROSS THE CLAIMS ON IT Fits inside what is free Fits by borrowing uses the ceiling up Does not fit needs the ceiling moved Which one wins not in the document The three white boxes are arithmetic. The dashed box is a judgement, and no budget contains it. Harivansh Packaging Limited is invented and every figure in this guide is illustrative.
A capital budget states one period, builds one total, and sorts every claim into fits, fits only by borrowing, or does not fit. The fourth box, which claim should win, is a judgement the document does not carry.

So what is a capital budget, actually?

The word budget makes people picture a spreadsheet with two hundred rows and a tab for every cost centre. A capital budget is smaller and stricter than that. A capital budget is one period, one total, and a division of that total across the claims made on it. Everything else people put in a budget document is commentary.

The shape is identical at household scale, and the numbers there are small enough to hold in mind. The household version comes first. A household runs on one salary. Each month an amount arrives. An amount is already sitting in the savings account. And there is an amount the household could raise against the gold in the locker if it truly had to, up to a limit it has quietly set for itself. Nobody wants to pledge all of it. Salary, savings and pledgeable gold together are the month's total. Then the rent goes out, the school fee goes out, and the vehicle instalment goes out, and not one of those three was ever a proposal. The money left over is what the new scooter, the shop deposit and the cousin's wedding are competing for. The remainder, and not the salary, is what the argument at the dinner table is actually about.

A company works the same way at a different scale. Harivansh Packaging Limited, an invented packaging manufacturer, generates a flow during the year, holds a balance at the start of it, and can borrow up to a ceiling it has set on its own leverage. Some spending happens regardless. The money left after that spending is the contested money.

Notice what this makes a budget, and what it does not make it. Nobody in the room will dispute that Rs 342 crore, Rs 140 crore and Rs 354 crore add to Rs 836 crore. The room is going to argue about whether 2.0 times is the right ceiling, whether upkeep truly costs Rs 138 crore, whether a flow measured ahead of every movement in working capitalThe money tied up in stock, in what customers owe and in what suppliers are owed, all of which swings during a year. How it is measured is covered in the statements material; what matters here is only whether the figure exists. movement is honest. The sum is not where the disagreement lives.

Try it out

A company holds Rs 140 crore of cash. Before reading further, predict: how much capital does it have available this year?

Financial Literacy Bootcamp — Fin Maverick

How big is the total, and who gets to decide?

The total has three parts and one honest gap. Counting the parts belongs to the comparison sheet, covered separately. A budget lives or dies on whether the reader can see its total. The three-line sum is worth restating for that reason.

The first part is what the business throws off during the period. For Harivansh Packaging, earnings before interest, tax, depreciation and amortisation (EBITDA)Operating profit measured ahead of interest, ahead of tax and ahead of the write-down on assets that last many years. Constructed in the statements material and used here as given. of Rs 477 crore, less finance costThe interest and related charges paid to the people who lent the business money, taken out of profit before tax. Settled in the statements material. of Rs 60 crore leaves, and so does tax of Rs 75 crore, and what survives both is Rs 342 crore. Rs 342 crore is a flow. The money lands across the twelve months rather than on the first morning.

Everything after that figure leans on it. Precision about what it is matters. Rs 342 crore is not a published cash number. Nothing in this record reports cash movements at all, so the figure is assembled from three lines of the profit ladder, and it wears the word proxy every time it appears. Two things are still ahead of it: the swing in working capital, and the maintenance spending that has to come out. Rs 342 crore is the most generous honest reading of one year's output, never money sitting available.

The second part is simpler than anything else here: Rs 140 crore is sitting in the account on day one. A balance, not a flow. The balance needs no derivation, it is the most certain number in the whole budget, and it can be spent exactly once.

The third part is a decision wearing the costume of a measurement. Borrowing capacity is the distance between today's net debt and the level the company has publicly promised itself it will stay under. Net debt here stands at Rs 600 crore. Put the promise at 2.0 times EBITDA and Rs 954 crore is permitted, leaving capacity of Rs 354 crore. Shift the promise by half a turn in either direction, and this quantity swings by hundreds of crore. Nothing whatever changes inside the business. The budget therefore prints three versions of the capacity instead of one.

The stated ceiling on net debtPermitted net debtBorrowing capacityThree-part total
1.5 times EBITDARs 715.50 croreRs 115.50 croreRs 597.50 crore
2.0 times EBITDA, used throughout belowRs 954 croreRs 354 croreRs 836 crore
2.5 times EBITDARs 1,192.50 croreRs 592.50 croreRs 1,074.50 crore
Three quantities, stacked into one total of Rs 836 crore at the 2.0 times ceiling. Two of the three are facts. The third is a policy. GENERATED Rs 342 crore HELD Rs 140 crore BORROWABLE Rs 354 crore a flow, arriving across the year a balance a policy, not a fact about the business Rs 836 crore THE GAP, WRITTEN INTO THE BUDGET RATHER THAN FILLED No working capital movement is published, so Rs 342 crore is generation, not cash available. Harivansh Packaging Limited is invented. The 1.5, 2.0 and 2.5 times ceilings are terms of an invented facility.
The total is a sum of three quantities that behave differently, and the third of them moves with a policy rather than with the business. Every argument about the size of a budget is an argument about one of the three.

Now the gap. The absence matters more than its single blank cell suggests. Nothing published for this business reports how stock, customer balances and supplier balances moved during the year, nor what it spent on capacity. So a year that ties up an extra Rs 40 crore in those balances hands over materially less than a year that frees Rs 40 crore from them, and the record refuses to say which year this was. A budget records that absence as a line with no figure against it, rather than proceeding as though the missing number were nil. A believable swing dropped into the empty cell does three things at once: the total shifts, every fit judgement resting on the total shifts with it, and nothing in the document marks that a number was manufactured.

Try it out

The budget shows a line reading "movement in working capital" with nothing in the amount column. What has the preparer done?

Which claims never had to be proposed?

Here is where a budget separates itself from a comparison sheet. The sheet lists every claim side by side so they can be looked at together. The budget takes some of them off the top before the looking starts.

Three kinds of spending land on the period without ever having been argued for. Keeping the existing plant capable of what it already does. Commitments signed in some earlier period that fall due inside this one. And repayments where a stated sum is owed on a stated date. No meeting has the power to reschedule one. Committed claims are not proposals, they do not compete, and a budget that puts them in the queue alongside the proposals has misdescribed the problem in its first line.

Go back to the household for a moment. The water pump gives out in April. Nobody pitched the pump, nobody built a case for the pump, nobody compared its return against the scooter, and the plumber gets paid regardless of what anybody thinks. Suppose the household instead writes down its total for the month and starts weighing the scooter against the shop deposit without first setting aside the rent and the pump. Such a conversation can be conducted with great care and still be about money that was never there.

For Harivansh Packaging the committed claim is maintenance spending, and here the record makes life awkward in a way worth being honest about. Nothing is published anywhere about what this business spends on its capacity, so the line has to borrow a figure from depreciation and amortisationAn accounting charge that writes down what was paid for durable equipment, a slice at a time, over the period it stays in service. Settled in the statements material. and stand at Rs 138 crore, with the word proxy written beside it in the cell itself. The two quantities are genuinely not the same thing. One looks backwards at equipment already bought and spreads its cost out; the other looks forward at what next year's upkeep will cost. The two figures tend to land near each other. The closeness is what makes the substitution tolerable and also what makes it easy to forget. Separating upkeep spending from growth spending is set out under maintenance and growth capital expenditure.

The repayment line is thinner still, and the budget admits it. Total borrowings of Rs 740 crore are known. No maturity split is published. How much of that pile matures inside these twelve months is therefore unknown. So the row goes on with an empty amount column and its reason written alongside, in the same shape as the working capital row above. Two blanks on one printed sheet read as carelessness until it becomes clear that a guess in either one would change which claims fit.

Now do the subtraction, one line at a time. Generation of Rs 342 crore less committed maintenance of Rs 138 crore leaves Rs 204 crore. Add the Rs 140 crore of cash held, and Rs 344 crore is what the competing uses are actually arguing over before anybody borrows a rupee. The business handles Rs 3,180 crore of revenue in the year. The contested money is roughly a ninth of that.

From what the business makes to what anyone is arguing over GENERATED Rs 342 crore LESS Rs 138 crore committed to maintenance, proxied at depreciation and amortisation FREE Rs 204 crore plus cash Rs 140 crore IN CONTENTION Rs 344 crore FOR SCALE Revenue for the year Rs 3,180 crore Genuinely contested, before borrowing Rs 344 crore Roughly one rupee in nine of what the business handles. All bars share one scale. Invented business, illustrative figures throughout.
Of about Rs 342 crore generated, Rs 138 crore is committed to maintenance before anyone proposes anything, so roughly Rs 204 crore of generation plus Rs 140 crore of cash is the money the competing uses are actually arguing over.
Try it out

Maintenance spending of Rs 138 crore has not been proposed by anyone and nobody is arguing for it. Where does it go in the budget?

Investment Banking Analyst Bootcamp — Fin Maverick

Why is an order not a ranking?

Once the committed claims are out, the remaining claims get put in an order. Ordering is the point at which most budget documents quietly stop being arithmetic and start being an argument, usually without anybody noticing that it happened.

Claims get ordered by two things, and neither of them is merit. The first is when the money is actually needed. A payment due in the second month sits ahead of one due in the eleventh, not because it is better but because a period runs in sequence and cash arrives across it. The second is which claims foreclose others. If committing to one use consumes the capacity a second use would have needed, then the second use has to be considered before the first is signed, or it will never be considered at all.

A queue is a scheduling device and a ranking is a judgement, and presenting the first as the second is how a budget begins making decisions it was never entitled to make. The two documents look identical. Both are a list of claims, one under another, with the biggest heading in the same font. A row's position means one thing on a schedule and another on a ranking, and the reader is almost never told which document they are holding.

The household version is sharp here. Suppose the school fee is due in June and the shop deposit is due in November. The fee goes first on the list. Nobody would say the list proves education matters more than the shop, and yet at a board table, with the same list drawn in a nicer typeface, somebody always does.

Same four rows. Same order. Two completely different documents. A QUEUE: WHEN IS THE MONEY NEEDED 1. Repayment falling due early 2. Project equity, drawn in stages 3. Return of capital to holders 4. Acquisition, timing not the company's Says: this is the sequence cash is called in. Says nothing about which use is better. A RANKING: WHICH CLAIM IS BEST 1. Repayment falling due early 2. Project equity, drawn in stages 3. Return of capital to holders 4. Acquisition, timing not the company's Claims a judgement the arithmetic never made. Nobody signed it. Nobody can unsign it. The heading is the only difference, and headings are what nobody reads.
An ordered list of claims carries no information about merit, yet the schedule and the ranking are the same four rows in the same sequence. Only the heading separates a scheduling device from a judgement nobody made.
Try it out

Two claims appear in order on a capital budget, one above the other. Does that mean the first one is better?

Private Equity Analyst Bootcamp — Fin Maverick

Which of the three constraints is actually binding?

A budget has a stopping point. Somewhere down the list there is a claim that cannot be funded, and something specific is stopping it. Naming that thing is one of the two or three genuinely useful outputs a budget produces. Everybody in the room already believes they know the answer, so the naming gets skipped constantly.

There are three candidates and they have to be tested one at a time.

Cash. Is there a rupee left in the account? For Harivansh Packaging there is. Rs 140 crore sits there untouched at the start of the period, and the generation keeps arriving. Cash is not what stops anything here.

The leverage ceiling. Would signing the next commitment push net debt past the line the company drew for itself and told people about? At 2.0 times EBITDA the permitted level is Rs 954 crore, net debt today is Rs 600 crore, and the capacity is therefore Rs 354 crore. A ceiling of the company's own choosing is not for that reason a soft one. A company that has told the market where it will stop and then steps past it has spent something that does not appear on any balance sheet.

A covenantA term written into a borrowing agreement that restricts what the borrower may do while the borrowing is outstanding. The terms of any real agreement are a matter for that document. in an existing facility. A borrowing agreement can contain a term that bites before either of the other two does, and when it does it is not negotiable at the pace of a budget meeting. The covenant used here is a term of an invented facility.

The binding constraint is very often not the one people quote: a company can be full of cash and out of headroom, or heavy with headroom and out of cash, and the budget's job is to say which. The two states look completely different from the inside and completely alike in a summary. A good budget therefore carries three tests and one named answer rather than a vague sentence about being constrained.

Test all three. Name one. Do not assume. THE NEXT CLAIM needs Rs 1,000 crore Is there cash left? Rs 140 crore, untouched NOT BINDING Is there room to the ceiling? Rs 354 crore, against Rs 1,000 crore THIS ONE BINDS Does a facility term bite first? a term of an invented facility READ THE DOCUMENT nothing stated here The useful output is the middle row, written in words: the ceiling is what stops this, not the bank balance. Invented business, invented facility, illustrative figures throughout.
Harivansh Packaging Limited is short of neither cash nor proposals, so what stops the acquisition sitting inside its budget is the leverage ceiling, and naming that is the output worth having.
Try it out

There is Rs 140 crore in the account, and Rs 354 crore of room beneath the stated ceiling. An acquisition wants Rs 1,000 crore of fresh borrowing behind it. Which of the three constraints actually stops it?

What happens to a claim bigger than one period?

Some claims are simply too large to be a decision about this year, and the rupee figure hides that completely. Rs 1,140 crore and Rs 140 crore are both numbers, both correct, and both look like the same kind of thing when set down side by side.

The cheapest fix available is to divide every claim by one period's generation and print the answer beside the rupee figure. Rs 342 crore is what this business produces in a year. So Rs 1,140 crore is 3.3 years of generation. Rs 540 crore of project equity is about 1.6 years. A repurchase or a repayment of Rs 140 crore is 0.41 years, and the committed maintenance is 0.40 years.

One caution attaches to that entire column, it leans the same way every time, and it is worth fixing in mind now. The denominator, Rs 342 crore, is the assembled proxy from earlier: nothing has yet been taken out of it for the swing in working capital, and nothing has been taken out for the Rs 138 crore of upkeep either. Every years figure in this guide is therefore a floor rather than a measure. Divide the same Rs 1,140 crore by the Rs 204 crore actually free after maintenance and it is 5.6 years, not 3.3, and the project equity moves from 1.6 years to 2.6. The truthful reading is a range with 3.3 years at its optimistic end, and this record does not carry what would be needed to close it. A floor is still useful: a claim that reaches into three periods at the most generous denominator available reaches into at least three.

Read that column and the character of each claim changes. A claim larger than one period's generation is a claim on periods that have not been budgeted yet, made by people who will not be in the room when the last of it is paid for. That is not an argument against large claims. Businesses have to make them. The years column is an argument for saying out loud that a three-year claim is being approved inside a one-year document. Saying it out loud changes how carefully the document gets read.

Expressing large claims in years of generation is close to free, takes one extra column, and almost nobody does it. The reason is uncomfortable: the column makes the biggest proposal look the most demanding, and the biggest proposal usually has the most senior sponsor.

Two questions at once: how much, and how many periods SIZE IN RUPEES, Rs 0 to Rs 1,200 crore YEARS OF GENERATION 1.0 year 2.0 years 3.0 years shaded band: one budget settles it alone Repurchase or repayment Rs 140 crore, 0.41 years Project equity, Tapti Crossing Rs 540 crore, about 1.6 years Paid to the sellers Rs 1,140 crore, 3.3 years Years are the rupee figure over Rs 342 crore of generation, which is a floor. Invented business, illustrative figures.
A claim's place is fixed by two things at once, how much of the total it consumes and how many periods it reaches into, and only the shaded band holds claims this budget can settle on its own.
Try it out

Predict before reading on. The acquisition costs Rs 1,140 crore paid to the sellers. Which budget does that claim belong to?

Financial Analyst Program Bootcamp — Fin Maverick Short Selling Mechanics — free micro-course from Fin Maverick

The budget for Harivansh Packaging Limited, written out

Here is the whole thing for one year, standalone, with every figure labelled and the two absences left as absences.

Four things this record does not carry, listed once so that no row below has to explain itself twice: there is no cash flow statement, no capital expenditure figure, no dividend or payout of any kind, and no run of prior years to read a trend from. Each of those shapes a cell in the tables that follow, and in every case the budget prints the absence rather than a number standing in for it.

The total for the periodAmountWhat kind of number this is
Generated: Rs 477 crore of EBITDA, after Rs 60 crore of interest and Rs 75 crore of taxRs 342 crorea flow, struck before any working capital movement
Movement in working capitalnot publishedabsent from the record; not assumed to be nil
Cash held at the start of the periodRs 140 crorea balance, spendable once
Borrowing capacity to a stated 2.0 times ceilingRs 354 crorea policy: Rs 954 crore permitted less Rs 600 crore of net debt
Total available at the stated ceilingRs 836 croreRs 597.50 crore at 1.5 times, Rs 1,074.50 crore at 2.5 times
Committed claims, out before anything is allocatedAmountBasis
Maintenance spendingRs 138 croreproxied at depreciation and amortisation, a proxy not a measurement
Scheduled repayment of borrowing falling duenot split outtotal borrowings of Rs 740 crore are known; the maturity split is not
Free generation, and the money genuinely in contention before borrowingRs 204 croreplus Rs 140 crore of cash gives Rs 344 crore

Put the borrowing capacity back on top of that and the whole total, after the one committed claim anybody could size has left it, is Rs 698 crore: Rs 836 crore of three-part total less the Rs 138 crore of upkeep. Rs 344 crore of it needs nobody's permission, and the remaining Rs 354 crore arrives only by moving net debt.

Now set the remaining claims against that. Each sorts into exactly one of three boxes, and the sort is the budget's real work.

ClaimRupeesYearsWhere it lands
A repurchase or a dividend, sized at the cash heldRs 140 crore0.41Fits. 41 per cent of one year's generation
Repayment of borrowing, sized at the cash heldRs 140 crore0.41Fits, on the same money as the row above it
Project equity, Tapti Crossing Infrastructure Private LimitedRs 540 crore1.58Fits only by borrowing Rs 196 crore of the Rs 354 crore capacity
Acquisition of Sundarban Polymers Private Limited, paid to the sellersRs 1,140 crore3.33Does not fit. Its Rs 1,000 crore of new borrowing is close to three times the capacity

Two notes on how those rows were sized. Sizing is where quiet inventions get in. The two Rs 140 crore rows are pinned to the cash balance for one reason and no other: not a rupee of distribution appears anywhere in this record, in any form or from any year, so no policy figure exists to size them with and the balance on hand is the only anchor that does not require inventing something. Rs 1,320 crore is enterprise value. The acquisition row runs on Rs 1,140 crore instead, and equity valueWhat actually reaches the sellers once the debt inside the business being bought is taken off the enterprise value. The bridge between the two was settled in the transaction valuation material. of Rs 1,140 crore is what the acquirer hands over. Quoting the larger figure as the price paid is the commonest error made about transaction numbers anywhere.

Fits, fits only by borrowing, or does not fit Rs 344 crore genuinely in contention before a rupee is borrowed Repurchase Rs 140 crore, fits inside the contested money Repayment Rs 140 crore, fits on that same money Project equity Rs 540 crore, needs Rs 196 crore borrowed Acquisition Rs 1,140 crore to the sellers, fits at no ceiling Capacity Rs 354 crore of borrowing capacity, for scale All bars share one scale, measured from the left edge of the bars. Invented business, illustrative figures.
A Rs 140 crore repurchase or repayment fits inside cash and generation, the Rs 540 crore of project equity fits only by using Rs 196 crore of borrowing capacity, and the acquisition fits nowhere in the total.

The finding, and it is not about the target

Look at the last row again. The acquisition is not a capital budget item at all. Nothing in this document can accommodate it, and no amount of reordering the claims above it will change that. The acquisition is a proposal to move the leverage ceiling, and calling it that is more useful than any further debate about where it belongs on the list.

Quote the move on whatever base the ceiling itself was struck on, or the sentence carries no meaning. The 2.0 times ceiling is a limit written against Harivansh Packaging alone: its own net debt, its own EBITDA, nobody else's. Hold that base fixed and follow the funding through. Borrowings of Rs 740 crore take on Rs 1,000 crore more, the Rs 140 crore of cash is spent down to nothing, and net debt for the acquirer by itself arrives at Rs 1,740 crore. Set against its own Rs 477 crore, that reads 3.65 times. The year opened at 1.26 times. The request, then, is permission to run at 3.65 times against a ceiling of 2.0 times.

A second reading is equally honest and has to wear a label wherever it shows up. A purchase of all the shares in Sundarban Polymers Private Limited brings that seller's own Rs 180 crore of net debt onto the combined books, taking the consolidated figure to Rs 1,920 crore against combined EBITDA of Rs 609 crore. The combined figure reads 3.15 times. Consolidated leverage is a different measure of a different thing, and it is not the measure the 2.0 times ceiling was ever struck on. Setting a consolidated ratio against a standalone ceiling is comparing two quantities that were never the same quantity.

Net debt to EBITDAReadingBasis, named every time
Where the year opened1.26 timesstandalone: Rs 600 crore over Rs 477 crore
The stated ceiling used in this budget2.0 timesstandalone, and the 1.5 and 2.5 times variants sit on the same base
Where the funded acquisition takes it3.65 timesstandalone: Rs 1,740 crore over the acquirer's own Rs 477 crore
The same transaction, consolidated3.15 timesRs 1,920 crore over combined EBITDA of Rs 609 crore, a different measure
The acquisition is a proposal about this scale, not about the list above 0.0x 4.0x 1.26x opened here 2.0x stated ceiling Rs 354 crore of capacity beneath it 3.65x where the funded deal lands, standalone 1.65 turns beyond the ceiling Consolidated, a different measure: Rs 1,920 crore over combined EBITDA of Rs 609 crore is 3.15 times, and it is not what the 2.0 times ceiling was struck on. Both rows are labelled, always. Invented transaction, illustrative figures. Scale runs 0.0 to 4.0 times, linear.
Measured the way the ceiling itself was measured, on the acquirer alone, the funded transaction carries leverage from 1.26 times up to 3.65 times, so the proposal is a request to move a 2.0 times ceiling by 1.65 turns.

The binding constraint has to be stated in words. The constraint is not cash: the Rs 140 crore is untouched and would still be untouched after the two Rs 140 crore claims were considered. Appetite is not the constraint either, and neither is the quality of the target. The target's quality is a separate question. The constraint is the ceiling. And whether to move a ceiling is a different question from whether an asset is worth buying, asked of different people, on a different timetable, with a different set of consequences if it goes wrong.

Try it out

A proposal needs close to three times the borrowing capacity available. Where does it go on the capital budget?

Who actually reads a budget this way, and what each of them is looking for

A lender reads it backwards. The lender goes to the constraint line first. A borrower who has not identified its own binding constraint will meet it by accident. Then it looks at the committed claims, the amounts that leave before any interest gets paid, and then at the years column. A borrower approving three years of generation inside a one-year document is telling the lender something about how the next three years will be financed.

An analyst reads it for the gap between the total and the claims. Rs 836 crore of total against a set of claims adding to well over twice that says the company is in a period of choosing, and periods of choosing are when the character of a business gets set. The analyst is not looking for the right answer. The analyst is looking for whether the company knows which question it is answering, and the labelled basis on the leverage row tells them that in one glance.

A holder reads it for what got foreclosed. Every rupee committed to one use is a rupee that will not be returned to them and will not be spent on the alternative, and the budget is the only document that ever shows those side by side with a total above them. Whether this transaction produces dilutionA fall in earnings per share brought about by something the company itself did, rather than by the business earning less. Whether this transaction produces one was worked through elsewhere in this subject area. of earnings per share is a separate question settled elsewhere, and a holder who reads only that number has taken the outcome without ever seeing the choice.

And a household reads it exactly the same way. The shape is worth carrying for that reason. Salary, savings, and what could be borrowed. Rent and fees out first. Then the argument, conducted over the remainder, with somebody occasionally pointing out that the thing being proposed would take four years of savings and therefore is not really this month's decision at all.

The budget carries every figure labelled and two absences left as absences. See which.

What does a budget produce, and what can it never produce?

A budget's output is short and worth listing exactly. A total, built rather than asserted, with all three parts visible. The committed claims removed before allocation. Every remaining claim sized in rupees and in years. Each claim sorted into fits, fits only by borrowing, or does not fit. The binding constraint named. And every absence left visible as an absence.

The choice is the one thing a budget cannot produce. The claims differ in kind, in certainty and in what they foreclose, and no arithmetic in a budget resolves any of those three. They differ in kind because returning capital to holders and buying a business are not the same species of act. The claims differ in certainty because Rs 140 crore repaid is a known outcome and Rs 1,140 crore of acquisition is a range with a long left tail. And they differ in what they foreclose. The repayment restores capacity; the acquisition consumes several periods of it.

So a budget presented as a decision has smuggled a judgement into a document that does not contain one. The tell is usually formatting: a summary line at the bottom, a row highlighted in a different colour, a claim placed first with no note saying why. None of those is arithmetic, and all of them are read as though they were.

What a finished capital budget has on it CAPITAL BUDGET, ONE PERIOD 1. The total, in three parts, each shown 2. Committed claims, removed before allocation 3. Every remaining claim, in rupees 4. The same claims, in years of generation 5. The binding constraint, named in words 6. Every missing figure, left visibly missing No ranking. No highlighted row. No summary line. NOT IN THE DOCUMENT Which claim wins They differ in kind, in certainty, and in what each one forecloses. A budget that answers the dashed box has added something it did not compute. Six items of arithmetic on the left. One judgement on the right, and it lives with people rather than in a document.
A finished budget shows the three-part total, the committed claims removed, the remaining claims in rupees and in years, the binding constraint named, and no ranking anywhere on it.
Try it out

The budget is complete. The total is built, the committed claims are out, every remaining claim is sized in rupees and in years, and the binding constraint is named. What is still missing?

Rebalancing: When, Why and What It Costs — free micro-course from Fin Maverick

What reopens a budget in the middle of a period?

A budget is written once and then reality arrives. Three things reopen it, and only three.

The first is a claim arriving that exceeds the total. Not a claim that is inconvenient or badly timed, but one the document has no room for at any ordering. The acquisition is exactly that, and recognising it as a reopening rather than as a line item is more useful than a long argument about where it fits. A budget can absorb a claim it did not expect. A budget cannot absorb a claim larger than itself, and pretending otherwise produces a document that has stopped describing anything.

The second is a constraint moving. If the leverage ceiling is reset from 2.0 times to 2.5 times, capacity goes from Rs 354 crore to Rs 592.50 crore and the total from Rs 836 crore to Rs 1,074.50 crore, and every fit judgement below has to be run again. Nothing about the business changed. A sentence in a policy changed, and the arithmetic beneath it moved by Rs 238.50 crore. A moving ceiling cuts the other way too: reset down to 1.5 times, it leaves Rs 115.50 crore of capacity, and the project equity that fitted by borrowing no longer fits at all.

The third is a committed claim turning out to be larger than it was booked at. Consuming contested money without any meeting taking place, an underbooked commitment is the quietest of the three and the most damaging. Maintenance carried at Rs 138 crore that actually costs Rs 180 crore has taken Rs 42 crore out of the Rs 204 crore of free generation, a fifth of it, and nobody proposed the increase or approved it. The same happens when a commitment agreed in an earlier period lands heavier than booked, or when an earn-outA further amount payable to sellers only if the business bought reaches an agreed level of performance after completion. How one is drafted and measured belongs to the documentation material. agreed in a past transaction becomes payable.

Reopening a budget is not a failure of the budget; refusing to reopen one is. A document written against a total that no longer exists keeps producing fit judgements that are all wrong in the same direction, and it looks exactly as authoritative as it did on the day it was correct.

Try it out

Name one thing that reopens a capital budget in the middle of a period.

The error: sizing the total on one of its three parts

Somebody prepares the first draft. The preparer opens the balance sheet, finds Rs 140 crore of cash, writes it at the top, and concludes that Rs 140 crore is the year's capital. Everything larger gets rejected on the spot, politely and quickly, and the rejections all look defensible because the total looked like a fact.

The Rs 342 crore the business generates during the period was left out, and so was the Rs 354 crore of capacity to the stated ceiling. The real total at that ceiling is Rs 836 crore, about six times the figure used. Rs 696 crore of capital was ruled out by an omission rather than by a decision.

The mirror error is just as common and costs more. Size the total on capacity alone, treat Rs 354 crore of borrowing capacity as though it were free capital sitting in an account, and forget that Rs 138 crore of the generation was committed to maintenance before anybody proposed anything. Such a draft commits to uses that were never affordable, and the shortfall shows up later as a scramble rather than as a decision.

A total with no workings beneath it looks identical whether it is right or wrong, so neither error is visible in the finished document. The fix is that the total is never written as a figure. The total is written as a short sum with all three parts and the committed claims shown beneath it. Four lines make both errors impossible to commit silently.

One related error belongs here. Somebody quotes post-transaction leverage as 2.86 times. The quote puts the acquirer's own standalone net debt of Rs 1,740 crore over the combined EBITDA of Rs 609 crore. The figure is wrong on both bases at once: standalone it is 3.65 times and consolidated it is 3.15 times, and 2.86 times measures nothing. A mixed basis understates leverage while looking perfectly derived. The combination is dangerous in a document whose whole purpose is to say what is affordable.

Two opposite errors. One document. It looks the same either way. THE CORRECT TOTAL Rs 836 crore, three parts SIZED ON CASH ALONE Rs 140 crore. Rs 696 crore ruled out by omission. SIZED ON CAPACITY ALONE Rs 354 crore, borrowed money treated as free. And Rs 138 crore of committed maintenance forgotten underneath it. First draft forgoes what was affordable. Second commits to what was not. The cure is four lines of sum, not a better number. Bars to scale. Invented business, illustrative figures.
Sizing the total on one of its three parts produces two opposite errors, and the budget document looks identical in both cases because a bare total carries no workings.
Jurisdiction

What is routed rather than stated here

Dividing a finite total across competing claims is arithmetic and travels anywhere. The rule set around it does not. Whatever a listed company has to place in front of the market before committing capital of this size sits with the Securities and Exchange Board of India, at sebi.gov.in. Whatever a company must resolve and file to act at all sits with the Ministry of Corporate Affairs, at mca.gov.in. Anything turning on how a figure is taxed sits with the income tax authority, at incometaxindia.gov.in, and the Rs 75 crore of tax used above is this invented company's own charge for one year rather than any published rate. Where a covenant appears it is a term of an invented facility, described only as a possible binding constraint. Each threshold, period, approval requirement and filing obligation is read at its source before it is relied on.

Where this guide stops. The comparison sheet, and the separation of growth spending from maintenance spending, are covered separately and are not redone here; this guide only divides a total and names what stops it. Returning capital to holders, and the closing comparison between repaying borrowing and repurchasing shares, are covered separately. How a project is appraised by discounting what it will produce belongs to the material on valuation method and is applied here rather than rebuilt. How this acquisition was negotiated, papered and completed sits separately in this subject area, and the toll road's ring-fenced structure sits in the material on project financing. Whether Harivansh Packaging Limited should buy anything, repay anything or return anything is not settled here, because the budget ends with the claims sized, ordered and constrained, and the choice belongs to the people holding information no published figure carries.
Rebalancing: When, Why and What It Costs teaches you to choose a rebalancing rule and say what it buys and what it costs.

What would be checked, and where

The pool, the ceilings, the claims and the business they belong to were all written for teaching, and the three-part sum is one way of setting out the job rather than anybody's stated method. The short table below records where a reader goes to check the conditions named here.

What is being checkedWhere it is heldSite
What has to be placed in front of the market before capital of this size is committedSecurities and Exchange Board of Indiasebi.gov.in
What a company must resolve and file in order to act at allMinistry of Corporate Affairsmca.gov.in
How a figure is taxed, which decides whether two amounts belong in one columnIncome tax authorityincometaxindia.gov.in
The three-part total, the committed claims, the three-way sort and every rupee in themThis platformwritten here, invented throughout

Harivansh Packaging Limited, Sundarban Polymers Private Limited, Tapti Crossing Infrastructure Private Limited, Devyani Kulkarni and Ashwin Rege are invented.
Educational material. Not advice on any investment, tax, budget or market position.

← PreviousNext →
Fin Maverick Micro CoursesExplore Micro Courses
Fin Maverick BootcampsExplore Bootcamps
Fin Maverick

Finance education that ends in a job, not a certificate that gathers dust. Built for young India.

LEARN
CalculatorsFrameworksComparisonsCareersShowdown
RESOURCES
All CoursesMicro CoursesBootcampsInternships
COMPANY
AboutJob openingPartnership
LEGAL
Privacy PolicyTerms & ConditionsContent LicenseReturn & Refund Policy
© 2026 FIN MAVERICK / BUILT FOR INDIA.DO FINANCE, DO NOT JUST READ ABOUT IT.