Case 047Project and real asset financeHard
A toll road with a 15-year concession is sized for debt at 1.3 times cover on its base case. How much can it borrow, and what happens to cover if traffic comes in 15% below the forecast?
1The situation
Varsaal Expressways holds a 15-year concession to toll a 120 km highway, after which the road returns to the state. The traffic consultant's base case gives toll revenue of Rs 200 crore a year; operating and maintenance costs are Rs 40 crore a year under a fixed-price contract. Treat both as flat over the concession, and ignore tax, for simplicity.
Lenders size the loan so that cash available for debt service covers debt service at least 1.3 times in every year. Interest is 10%, and the loan is repaid in equal annual instalments of interest and principal over the full 15 years. The credit committee asks what happens if traffic comes in 15% below the consultant's base case.
2Your task
What is the maximum debt, what is cover if traffic falls 15% short, and how would you change the structure?
Quick check
Traffic comes in 15% below base. Roughly where does cover land?
Worked solution
Try it on paper, then open one step at a time.
30-second answerThe answer to give first
The road can carry about Rs 936 crore of debt, and a 15% traffic miss cuts cover from 1.30x to about 1.06x. Cash available for debt service is Rs 160 crore, so debt service can be Rs 123.1 crore a year, which supports Rs 936 crore at 10% over 15 years. Because operating costs are fixed, the miss removes 18.75% of cash and over four fifths of the cushion. Lenders should size on a downside case, not the base case.
Step 1How much debt can the toll road carry?
A bank lending to a family looks at what is left each month after rent and groceries, and lets the EMI take only part of it, so a bad month does not mean a missed payment. Project lenders do the same with a ratio. Cash available for debt service is Rs 200 crore less Rs 40 crore, Rs 160 crore, and at 1.3 times cover, debt service can be at most 160 / 1.3 = Rs 123.1 crore a year. At 10% over 15 years, each rupee of yearly instalment repays Rs 7.61 of loan today, so the maximum debt is Rs 123.1 crore x 7.6061 = Rs 936.1 crore.
| \text{CFADS} | cash available for debt service: toll revenue less operating costs, Rs 160 crore |
| \text{DSCR}_{min} | the minimum cover lenders accept, 1.3 times |
| r, n | interest rate, 10%, and years of repayment, 15 |
In the first year, Rs 93.6 crore of the Rs 123.1 crore instalment is interest and only Rs 29.5 crore repays principal. That is normal for an equal-instalment loan, and it means the debt stays large for most of the concession.
Step 2What happens to cover if traffic comes in 15% below base?
A 15% traffic miss takes revenue from Rs 200 crore to Rs 170 crore, but the maintenance contract still costs Rs 40 crore. Cash falls from Rs 160 crore to Rs 130 crore, an 18.75% drop from a 15% miss, and cover falls from 1.30x to 1.06x. This is operating leverageThe effect of fixed costs on profit: when costs do not fall with revenue, a given percentage fall in revenue causes a larger percentage fall in cash.: fixed costs make cash move more than traffic. The road still pays, but the cushion above debt service shrinks from Rs 36.9 crore to Rs 6.9 crore, which is 81% of it gone.
| Rs crore a year | Base case | Traffic 15% below |
|---|---|---|
| Toll revenue | 200 | 170 |
| Operating and maintenance cost | (40) | (40) |
| Cash available for debt service | 160 | 130 |
| Debt service on Rs 936 crore | (123.1) | (123.1) |
| Cushion | 36.9 | 6.9 |
| Debt service cover | 1.30x | 1.06x |
Step 3How much traffic miss can the structure take, and what would you change?
Work backwards from the levels that matter. Cover reaches 1.00x, where the road can no longer pay in full, at a traffic miss of 18.5%, only 3.5 points beyond the stress the committee asked about. Most project loans also have a lock-upA cover level, above default, below which the project may not pay dividends to its sponsor; cash is kept inside the project to protect lenders. test; taking it at an illustrative 1.15x, the sponsor stops receiving dividends at a miss of just 9.2%. Traffic forecasts for new roads rest on assumptions about growth and diversion from other routes, and they are often missed in the early years, so these are not remote cases.
Three changes would make the loan sturdier. First, size on a downside case: if lenders take traffic 10% below base as their sizing case, cash is Rs 140 crore and maximum debt falls to about Rs 819 crore, Rs 117 crore less, with the sponsor putting in that much more equity. Second, require a debt service reserve of six months' payments, about Rs 62 crore, which can pay through a bad year without default. Third, end the loan two or three years before the concession expires, so a slow start can be caught up before the road is handed back. The limitation is that each change lowers the sponsor's return, and the sponsor will push back; the lender's job is to show what the traffic miss costs and price or structure for it.
Where candidates lose it
The common error is to scale cover in proportion to traffic: 1.30 times 0.85 is 1.10x. Fixed operating costs mean cash falls faster than revenue, so the true figure is 1.06x.
The second is to read 1.06x as safe because it is above 1.0. The cushion has fallen from Rs 36.9 crore to Rs 6.9 crore, and a further 3.5 points of traffic miss would leave the road unable to pay.
What the interviewer asks next
- Size the debt on a 13-year repayment that leaves a two-year tail before the concession ends. How much less can the road borrow?
- Toll rates rise with inflation but maintenance costs rise faster. How does that change the stress?
- What does a six-month debt service reserve buy the lenders in the stressed case?
Company names and figures are illustrative.
